Laserfiche WebLink
Riverside Public Utilities <br />Open Capital Work Order Summary Report - Electric Fund <br />March -23 <br />Open Work Orders/Projects with Budgeted or Actual expenditures > $200,000 <br />OVERHEAD <br />2,174,000 <br />1503112 <br />Plaza substation - Circuit 450 <br />Year to Date <br />Life to Date <br />1808449 <br />Plaza Substation - Circuit 448 <br />Job Status <br />Plaza Substation 4kV to 12kV <br />Project / Subproject <br />Subtotal of OVERHEAD <br />Board <br />Board <br />591,039 <br />Total <br />Total <br />Available <br />Last <br />(Based on Proj. Est.) <br />973,000 <br />973,000 <br />Project Description <br />545,842 <br />427,158 <br />09/30/21 <br />56% <br />99% <br />Completed. <br />12/22/20 <br />Project Status <br />4,450,000 <br />375,027 <br />or WO <br />3,520,426 <br />Approval <br />Approved <br />Project <br />as of <br />as of <br />Balance <br />Activity <br />376,094 <br />5,023,439 <br />4,611,561 <br />3,952,348 <br />676,652 <br />06/25/21 <br />1,300,000 <br />1,300,000 <br />Spent <br />%Completed <br />(139,874) <br />09/16/22 <br />111% <br />Date <br />Estimate(') <br />I Estimate (2) <br />3/31/2023 <br />3/31/2023 <br />1 <br />1 Date <br />405,285 <br />03/17/23 <br />43% <br />Open Work Orders/Projects with Budgeted or Actual expenditures > $200,000 <br />OVERHEAD <br />2,174,000 <br />1503112 <br />Plaza substation - Circuit 450 <br />1708708 <br />Plaza Sub 4/12kV Conversion Circuit 441 <br />1808449 <br />Plaza Substation - Circuit 448 <br />1904777 <br />Plaza Substation 4kV to 12kV <br />2,038,000 <br />Subtotal of OVERHEAD <br />UNDERGROUND <br />1619972 <br />2009293 <br />1904200 <br />1910967 <br />SUBSTATION <br />1814007 <br />1816163 <br />1826061 <br />1826767 <br />1822318 <br />1810532 <br />1906356 <br />1910518 <br />2002530 <br />2123497 <br />2202600 <br />Canyon Crest Cable Replacement Area 1 F, Phase 3 Project <br />Switch Cable Replacement Project Phase I <br />Canyon Crest Cable Replacement Area 5 Project <br />01/28/19 <br />2,174,000 <br />2,174,000 <br />1,067 <br />2,101,062 <br />72,938 <br />03/16/23 <br />97% <br />95% <br />Pending cutover and as-builts <br />08/12/19 <br />2,038,000 <br />2,038,000 <br />- <br />1,446,961 <br />591,039 <br />05/12/22 <br />71% <br />95% <br />Pending as-builts <br />07/09/18 <br />973,000 <br />973,000 <br />- <br />545,842 <br />427,158 <br />09/30/21 <br />56% <br />99% <br />Completed. <br />12/22/20 <br />4,450,000 <br />4,450,000 <br />375,027 <br />929,574 <br />3,520,426 <br />03/23/23 <br />21% <br />20% <br />In construction. <br />9,635,000 <br />376,094 <br />5,023,439 <br />4,611,561 <br />3,952,348 <br />676,652 <br />06/25/21 <br />1,300,000 <br />1,300,000 <br />10,930 <br />1,439,874 <br />(139,874) <br />09/16/22 <br />111% <br />90% <br />Construction complete. Crews pulling cable. <br />07/26/21 <br />705,000 <br />705,000 <br />133,325 <br />299,715 <br />405,285 <br />03/17/23 <br />43% <br />85% <br />In construction. <br />05/09/22 <br />2,115,000 <br />2,115,000 <br />939,374 <br />1,730,435 <br />384,565 <br />03/17/23 <br />82% <br />50% <br />In construction. <br />Construction was complete and released to the crews <br />Gilbralter Drive Cable Replacement Project <br />08/08/22 <br />509,000 <br />509,000 <br />381,011 <br />482,323 <br />26,677 <br />03/08/23 <br />95% <br />90% <br />on December 14th with the exception of a CST lid. <br />Estimated time of completion for the lid is approx. 6 <br />weeks. <br />Subtotal of UNDERGROUND <br />4,629,000 <br />1,464,639 <br />3,952,348 <br />676,652 <br />Substation Capacitor Upgrade Project <br />01/22/18 <br />5,306,000 <br />5,306,000 <br />137,161 <br />5,198,318 <br />107,682 <br />02/16/23 <br />98% <br />99% <br />Completed. <br />Substation Automation Upgrade Project <br />02/26/18 <br />2,027,679 <br />2,027,679 <br />14,071 <br />1,802,949 <br />224,730 <br />03/16/23 <br />89% <br />90% <br />In implementation phase. <br />Riverside power plants Arc Flash Mitigation <br />06/11/18 <br />497,000 <br />497,000 <br />- <br />63,408 <br />433,592 <br />06/10/20 <br />13% <br />12% <br />In design. <br />Hunter Substation Replacement Project <br />01/14/19 <br />2,000,000 <br />2,000,000 <br />23,103 <br />1,280,806 <br />719,194 <br />03/02/23 <br />64% <br />70% <br />Submitted RFP to Purchasing for EPC contract <br />Multi Substation Transformer Upgrade/ Recondition <br />06/25/18 <br />3,082,617 <br />3,082,617 <br />15,642 <br />2,952,301 <br />130,316 <br />03/02/23 <br />96% <br />99% <br />Completed. <br />Freeman Switchgear and Transformer Upgrade <br />11/05/18 <br />5,463,000 <br />5,463,000 <br />1,536 <br />5,106,934 <br />356,067 <br />03/31/22 <br />93% <br />98% <br />Completed pending as-builts and updating standards. <br />Multi Substation - 69kV Circuit Breakers Replacement <br />09/23/19 <br />6,500,000 <br />6,500,000 <br />291,709 <br />5,357,059 <br />1,142,941 <br />03/13/23 <br />82% <br />80% <br />In implementation phase. <br />Substation Protection Support for Multiple Substations, with <br />11/25/19 <br />480,000 <br />480,000 <br />3,042 <br />206,473 <br />273,527 <br />12/13/22 <br />43% <br />45% <br />In implementation phase. <br />Stantec Consulting Services Inc. <br />Multi Substation Transformer Upgrade and Reconditioning <br />02/24/20 <br />1,883,000 <br />1,883,000 <br />- <br />1,817,998 <br />65,002 <br />06/09/22 <br />97% <br />99% <br />Completed. <br />Rohr Substation protection system upgrade project <br />09/13/21 <br />485,000 <br />485,000 <br />51,027 <br />142,199 <br />485,000 <br />02/27/23 <br />29% <br />30% <br />On hold. <br />Teleprotection Substation Infrastructure Upgrade Project <br />12/13/21 <br />544,378 <br />544,378 <br />22,418 <br />454,986 <br />89,392 <br />08/15/22 <br />84% <br />60% <br />In implementation phase. <br />1of3 <br />