Item 10 <br />Riverside Public Utilities <br />Open Capital Work Order Summary Report - Water Fund <br />June -20 <br />Open Work Orders/Projects with Budgeted or Actual expenditures > $200,000 <br />DISTRIBUTION PIPELINE <br />1615173 Water Cust. Development - 58 Magnolia Ctr. <br />1726679 Iowa Ave 12 -inch Water Main Extension <br />(3) (3) 237,767 262,912 (25,145) 03/31/18 111% <br />09/24/18 353,000 353,000 7,961 310,131 42,869 12/12/19 88% <br />1905091 <br />Iowa Ave 12 -inch Water Main Extension <br />09/24/18 <br />269,000 <br />269,000 <br />Year to Date <br />Life to Date <br />Water Service Lateral Replacement Program FY2019/20 <br />01/13/20 <br />Job Status <br />750,000 <br />Project / <br />Subproject <br />Project Description <br />Board <br />Board <br />788,000 <br />Total <br />Total <br />1912417 <br />Last <br />(Based on Proj. Est.) <br />Project Status <br />% <br />25,098 <br />or WO <br />Jo Jo Way Water Main Replacement Project <br />Approval <br />Approved <br />Project <br />as of <br />as of <br />Available <br />Activity <br />3,212,767 <br />694,517 <br />Date <br />Estimate') <br />Estimate�2) <br />06/30/2020 <br />06/30/2020 <br />Balance <br />Date <br />Spent <br />I Completed <br />09/23/19 <br />Open Work Orders/Projects with Budgeted or Actual expenditures > $200,000 <br />DISTRIBUTION PIPELINE <br />1615173 Water Cust. Development - 58 Magnolia Ctr. <br />1726679 Iowa Ave 12 -inch Water Main Extension <br />(3) (3) 237,767 262,912 (25,145) 03/31/18 111% <br />09/24/18 353,000 353,000 7,961 310,131 42,869 12/12/19 88% <br />1905091 <br />Iowa Ave 12 -inch Water Main Extension <br />09/24/18 <br />269,000 <br />269,000 <br />1,568,109 <br />2016734 <br />Water Service Lateral Replacement Program FY2019/20 <br />01/13/20 <br />750,000 <br />750,000 <br />- <br />2007552 <br />Scheuer Well Supply Main Replacement Project <br />01/13/20 <br />788,000 <br />788,000 <br />658,637 <br />1912417 <br />Royal Palm Water Main Replacement Project <br />03/09/20 <br />323,000 <br />323,000 <br />25,098 <br />1731943 <br />Jo Jo Way Water Main Replacement Project <br />03/23/20 <br />492,000 <br />492,000 <br />2,822 <br />Subtotal of DISTRIBUTION PIPELINE <br />3,212,767 <br />694,517 <br />DISTRIBUTION FACILITIES <br />1402756 <br />Mission Inn Booster Station Project <br />09/23/19 <br />2,120,000 <br />2,120,000 <br />809,796 <br />1403310 <br />Mission Inn Rezoning Pipeline Project <br />09/23/19 <br />3,625,000 <br />3,625,000 <br />1,838,457 <br />1524282 <br />Land Mobile Radio (LMR) system (Wtr Portion) <br />09/26/16 <br />3,000,000 <br />1,350,000 <br />- <br />1706279 <br />Wells & Cypress Water Main Replacement <br />06/24/19 <br />2,450,000 <br />2,450,000 <br />1,491,747 <br />1904589 <br />Potable Water Emergency Interconnection with the City of Norco <br />03/25/19 <br />340,000 <br />340,000 <br />88,468 <br />Subtotal of DISTRIBUTION FACILITIES <br />9,885,000 <br />4,228,469 <br />WATER SUPPLY <br />1722078 <br />Jackson St - Phase 1 & 2 Water Sites Retrofit <br />04/24/17 <br />434,370 <br />434,370 <br />13,937 <br />Subtotal of WATER SUPPLY <br />434,370 <br />13,937 <br />77,879 <br />191,121 <br />06/20/19 <br />29% <br />- <br />1,568,109 <br />12/11/19 <br />0% <br />658,637 <br />129,363 <br />03/05/20 <br />84% <br />47,013 <br />275,987 <br />11/28/19 <br />15% <br />35,639 <br />456,361 <br />04/20/20 <br />7% <br />1,392,211 <br />1,070,556 <br />5% <br />Approved by Board on April 13, 2020 <br />968,319 <br />1,151,681 <br />06/04/20 <br />46% <br />2,056,891 <br />1,568,109 <br />06/03/20 <br />57% <br />1,283,051 <br />66,949 <br />04/26/19 <br />95% <br />1,608,331 <br />841,669 <br />05/28/20 <br />66% <br />148,464 <br />191,536 <br />02/01/20 <br />44% <br />6,065,056 3,819,944 <br />90% <br />Completed, pending as-builts/mapping <br />98% <br />Final grade not set. FF still need to set <br />95% <br />final domestic services and vaults, after <br />90% <br />Public Works final grading. <br />100% <br />Blow off hydrants and air valve need final <br />placement once final grade complete. <br />Waiting for UCR for right-of-way <br />90% <br />approval. <br />0% <br />In implementation phase <br />100% <br />Completed <br />0% <br />Field forces on hold <br />5% <br />Approved by Board on April 13, 2020 <br />60% <br />In Construction. <br />98% <br />In Construction. <br />95% <br />Completed,pending commisioning. <br />95% <br />Under construction by City Forces <br />100% <br />Field forces complete <br />255,233 179,137 05/12/20 59% 34% In design / on hold <br />255,233 179,137 <br />1 of 2 <br />