Laserfiche WebLink
W A T E R E N E R G Y T I F F <br />RIVERSIDE PUBLIC UTILITIES <br />id& Board Memorandum <br />P U B L I C U T I L I T I E S <br />BOARD OF PUBLIC UTILITIES DATE: JUNE 10, 2019 <br />ITEM NO: 10 <br />SUBJECT: LA COLINA SWITCHGEAR 3 AND 4 REPLACEMENT PROJECT - WORK ORDER <br />NUMBER 1927285 IN THE AMOUNT OF $480,000 <br />ISSUE: <br />Approve Work Order Number 1927285 for the La Colina switchgear 3 and 4 replacement project in the <br />amount of $480,000. <br />RECOMMENDATION: <br />That the Board of Public Utilities approve Work Order No. 1927285 for La Colina switchgear 3 and 4 <br />replacement project in the amount of $480,000. <br />BACKGROUND: <br />Electrical substations (substations) are the joining of facilities between the distribution and transmission <br />systems. Substations house critical equipment and infrastructure such as substation power transformers, <br />switchgears, power circuit breakers, and protective relaying equipment. All this equipment within the <br />substation boundaries is vital for the reliable and optimum operation of the electric grid. <br />Substation equipment must be upgraded periodically to meet increasing electric power demand, maintain <br />safety, and improve system reliability. Several of the substation equipment in the Riverside Public Utilities <br />(RPU) system have exceeded, or are reaching, the end of their design life. Replacement of failed <br />equipment such as switchgears is very expensive and lengthy due to the design requirements and the <br />complexity of the manufacturing process. The failure of a single unit can result in a significant impact on <br />the electric system's reliability and the safety of employees and the public. <br />