RIVERSIDE PUBLIC UTILITIES <br /> W& Board Memorandum <br /> P U B L I C U T I L I T I E S <br /> BOARD OF PUBLIC UTILITIES DATE: May 20, 2011 <br /> ITEM NO: 3 <br /> SUBJECT: CHANGE ORDER NO. 2 TO PURCHASE ORDER NO. 112967 FOR OVERHEAD TO <br /> UNDERGROUND CONVERSION AT CHICAGO AVENUE AND MARTIN LUTHER <br /> KING BOULEVARD -WORK ORDER NO. 1022905 <br /> ISSUE: <br /> That the Board of Public Utilities consider approval of Change Order No. 2 to Purchase Order No. <br /> 112967, in the amount of$8,979.70 for replacement of one additional pole and installation of three street <br /> lights. <br /> RECOMMENDATION: <br /> That the Board of Public Utilities approve Change Order No. 2 to Purchase Order No. 112967, in the <br /> amount of$8,979.70. <br /> BACKGROUND: <br /> Work Order No. 1022905 for the overhead to underground conversion along Chicago Avenue and Martin <br /> Luther King Boulevard was issued to the Contractors' Panel for Energy Delivery work. Bids were opened <br /> on September 17, 2010 and Asplundh Tree Expert Company, the lowest responsive bidder, was <br /> awarded the bid in the amount of$268,443.80 by the issuance of Purchase Order No.112967. <br /> The work along Chicago Avenue and Martin Luther King Boulevard was required in order to eliminate <br /> interferences with the upcoming construction of the new 69kV circuit that will be constructed as part of <br /> the Sub Transmission Project (STP). <br /> Change Order No. 1, in the amount of $26,844.38 was issued on March 16, 2011 for replacing four <br /> additional poles due to General Order (G.O.) 95 compliance and additional trenching, conduit and <br /> structure additions due to conflicts with existing utilities. G.O. 95 is issued by the California Public <br /> Utilities Commission ("CPUC"). Although Riverside is not subject to CPUC jurisdiction, Riverside regards <br /> and follows the electrical transmission construction guidelines set forth in this general order as the <br /> industry's standard of care for inspection and maintenance of transmission lines and poles. <br /> Change Order No. 2, in the amount of $8,979.70 is requested to replace one additional pole to facilitate <br /> the new construction, as well as transferring and installing three street lights. Board authorization is <br /> required as the cumulative change order amount exceeds 10% of the original purchase order amount. <br /> No further change orders are anticipated as the work is complete. <br /> FISCAL IMPACT: <br /> The total contract is as follows: <br /> Percent <br /> Description Amount Change <br /> Original purchase order $268,443.80 <br /> Change order No. 1 _ $26,844.38 10.00% <br /> Change order No. 2 $8,979.70 3.35% <br /> Total $304,267.88 13.35% <br />