Laserfiche WebLink
q i R !• [ 1 <br /> RIVERSIDE PUBLIC UTILITIES <br /> Board Memorandum <br /> PUBLIC UTILITIES <br /> BOARD OF PUBLIC UTILITIES DATE: May 6, 2011 <br /> ITEM NO: 11 <br /> SUBJECT: RELOCATION OF OVERHEAD AND UNDERGROUND ELECTRIC FACILITIES <br /> FOR PUBLIC WORKS' IOWA AVENUE GRADE SEPARATION PROJECT - WORK <br /> ORDER NO. 080015-03 <br /> ISSUE: <br /> Board of Public Utilities approval is requested for Work Order No. 080015-03. <br /> RECOMMENDATION: <br /> That the Board of Public Utilities approve the estimated capital expenditure of $923,800 to relocate <br /> overhead and underground electrical equipment and structures (located at Iowa Avenue and Citrus <br /> Street)to accommodate new bridge construction for the Iowa Avenue Grade Separation Project. <br /> BACKGROUND: <br /> The electric system in this area is primarily overhead and includes both 12 kV distribution facilities and <br /> 69 kV transmission facilities. The construction of the Iowa Avenue bridge over the railroad tracks (grade <br /> separation) necessitates the removal of most of the overhead facilities and conversion to underground. <br /> A steel foundation pole will be installed to accommodate the 69 kV transmission lines, and a steel casing <br /> will be installed under the railroad tracks for current and future 12 kV distribution facilities. Pad-mounted <br /> devices will be installed to replace the overhead utilities that will be removed. <br /> The electrical engineering was performed by Riverside Public Utilities (RPU). All civil work including <br /> trenching, conduits and other infrastructure work will be performed by a contractor through the <br /> competitive bid process. Electrical work will be performed by RPU field forces. <br /> FISCAL IMPACT: <br /> The capital expenditure for the project is estimated to be $923,800, of which $256,360 will be reimbursed <br /> to the City by AT&T for proposed joint trench facilities, leaving a net cost to RPU of $667,440. This <br /> includes all construction, construction management, inspection and design, and contingencies as <br /> summarized in the following table: <br /> % of <br /> Total <br /> Design, Construction Management, Inspection $72,000 8% <br /> Construction-RPU Electrical Work$ Materials $226,500 25% <br /> Construction-Electric Conduit & Structures $580,300 62% <br /> Contingency $45,300 5% <br /> Subtotal. $923,800 100% <br /> Funds are budgeted and available for this project in the Cable Replacement Account No. 6130000- <br /> 470619. <br />