W A T E R E N E k G Y 1 F F <br /> �-- RIVERSIDE PUBLIC UTILITIES <br /> Board Memorandum <br /> P U B L I C U T I L I T I E S <br /> BOARD OF PUBLIC UTILITIES DATE. .July 20, 2012 <br /> ITEM NO: 3 <br /> SUBJECT: CHANGE ORDER NO.9 TO PURCHASE ORDER NO. 115649 FOR CONSTRUCTION <br /> OF PHASE 2C OF THE SUB-TRANSMISSION PROJECT AND THE RELOCATION OF <br /> THE OVERHEAD ELECTRICAL FACILITIES IN CONFLICT WITH THE CALTRANS <br /> 91 HOV PROJECT BETWEEN NINTH AND FIFTEENTH STREETS; PARTIAL <br /> REIMBURSEMENT BY ROTC <br /> ISSUE: <br /> Board of Public Utilities approval is requested for Change Order No. 9 to Purchase Order No. 115649 in the <br /> amount of$12,771.26 for additional work related to unanticipated design modifications and field conditions. <br /> RECOMMENDATION' <br /> That the Board of Public Utilities approve Change Order No. 9 to Purchase Order No. 115649 in the amount <br /> of$12,771.25. <br /> BACKGROUND: <br /> On May 6, 2011, the Board of Public Utilities awarded a contract to International Line Builders, Inc. (ILB) of <br /> Riverside,California to construct Phase 2C,a portion of the Sub-Transmission Project(STP)between the 91 <br /> Freeway and Vine Street and from Ninth to Eleventh Streets and to relocate the overhead electrical facilities <br /> along both sides of the freeway between Eleventh and Fifteenth Streets that were in potential conflict with the <br /> 91 HOV project. The projects shared common elements making it necessary to award the work to a single <br /> contractor. The cost of work was prorated between the projects. Approximately 10%of the cost of work was <br /> charged to the STP and 90%to the Caltrans project. <br /> Purchase Order No. 115649 was issued for an amount of $1,225,187 with a change order limit of <br /> $100,000.00 plus 1%of the original PO amount totaling$112,251.87. Eight change orders have been issued <br /> to date equaling the change order limit. Change Order No. 9 for$12,771.26 exceeds the limit and requires <br /> Board of Public Utilities approval. <br /> Change Order % Change <br /> Description net Balance Compared <br /> increase/ to Original <br /> Decrease P.Q. <br /> Original Purchase Order ---- $1,225,187.00 0% <br /> Change Order(C.O.) No. 1 - accounting correction ---- ---- 0% <br /> C.O. No. 2- eliminated bid units due to_design changes. ($244,685.50)__ $244,685.50 20% <br /> C.O. No. 3-design changes related to the 91 HDV project $248,239.70 $3,554.20 0% <br /> C.O. No. 4 - minor field change $3,423.63 $6,977.83 0% <br /> C.D. No. 5 - minor field changes $21,086.01_ $28,063.84 2% <br /> C.O. No. 6 -significant changes due to field conditions $84,188.03 $112,251.87 9% <br /> C.O. No. 7 -adjusted quantities due to design changes _($17,044.73) $95,207.14 8% <br /> C.O No. 8 - miscellaneous field changes, partial payment $17,044.73 $112,251.87 9% <br /> C.O. No. 9- miscellaneous field changes, balance due $12,771.26 $125,023.1_3 10% <br /> Original Purchase Order plus Change Orders $1,350,210.13 10% <br />