W A T E R <br />ENERGY LIFE <br />WI <br />Wig <br />PUBLIC UTILITIES <br />RIVERSIDE PUBLIC UTILITIES <br />Board Memorandum <br />BOARD OF PUBLIC UTILITIES <br />DATE: OCTOBER 3, 2014 <br />ITEM NO: 11 <br />SUBJECT: CONSTRUCTION OF THE WOHLSTETTER AND COOK WATER MAIN <br />REPLACEMENT PROJECT — WORK ORDER NO. 1422199 <br />ISSUE: <br />The item for Board of Public Utilities consideration is approval of the capital expenditure in the amount <br />of $1,136,000 to construct the Wohlstetter and Cook Water Main Replacement Project. <br />RECOMMENDATION: <br />That the Board of Public Utilities approve the capital expenditure of $1,136,000 for Work Order No. <br />1422199, which includes all design, construction, paving, contract administration, inspection and <br />construction contingency costs for the Wohlstetter and Cook Water Main Replacement Project. <br />BACKGROUND: <br />The construction of the Wohlstetter and Cook Water Main Replacement Project is part of Riverside <br />Public Utilities' (RPU) on -going water main replacement program to replace old and high priority, leaky <br />mains. The project area consists of existing 4 -inch and 6 -inch asbestos cement pipe and 6 -inch and 8- <br />inch steel pipe water mains that were installed between 1947 and 1965 and have recently experienced <br />numerous Teaks requiring repairs. Based on their leak history, these water pipelines have been <br />identified as high priorities for replacement. <br />The work will entail the construction of approximately 3,790 linear feet of 8 -inch ductile iron pipe, nine <br />fire hydrants, 61 service tie -overs and ten system connections. The work identified will be constructed <br />by the Water Division's field forces. Other than routine service tie - overs, this project is not expected to <br />disrupt service to RPU water customers. <br />Once the new water pipelines are installed, RPU will be responsible for standard trench repaving per <br />the Public Works Department standard. Staff will solicit paving bids for paving the trench area from <br />RPU's Paving Contractor Panel. A budgetary estimate for the paving work has been included in this <br />authorization. <br />The work is scheduled to occur during daytime hours. A portion of the work is located in the vicinity of <br />the Foothill Elementary and Wells Middle Schools. Work affecting the schools will be coordinated with <br />the school's respective bell schedules to minimize impacts. <br />