Laserfiche WebLink
RIVERSIDE PUBLIC UTILITIES <br />Board Memorandum <br />P U B L I C U T I L I T I F$ <br />BOARD OF PUBLIC UTILITIES DATE: JULY 10, 2015 <br />ITEM NO: 4 <br />File ID — 15 -2151 - C <br />SUBJECT: RELOCATION OF OVERHEAD ELECTRICAL FACILITIES AT VAN BUREN <br />BOULEVARD FROM COLORADO TO AUDREY AVENUES — WORK ORDER NO. <br />1515769 FOR $105,000 <br />ISSUE: <br />The issue for the Board of Public Utilities consideration is to approve a capital expenditure in the amount <br />of $105,000 for Work Order No.1515769 to relocate overhead electrical facilities along Van Buren <br />Boulevard from Colorado to Audrey Avenues. <br />RECOMMENDATION: <br />That the Board of Public Utilities approve the estimated capital expenditure of $105,000 for Work Order <br />No. 1515769 to relocate overhead electrical facilities along Van Buren Boulevard from Colorado to <br />Audrey Avenues as part of the Van Buren Boulevard Street Improvements resulting from the Walmart <br />Renovation Project (Project). <br />BACKGROUND: <br />The Project will relocate existing overhead electrical distribution facilities to accommodate the Van Buren <br />Boulevard Street Improvements resulting from the Walmart Renovation Project. The work includes the <br />relocation of seven distribution poles, one overhead switch, two overhead pole mounted transformers, <br />one pole mounted capacitor bank, one streetlight standard and related electrical distribution facilities. <br />Riverside Public Utilities (RPU) engineering staff performed the design to eliminate any negative visual <br />impacts to the project and surrounding area, with sensitivity to the existing neighborhood, and within City <br />Planning guidelines for the designated area of the Project. <br />The project breakdown is proposed as follows: <br />Project Breakdown <br />Engineering Performed By: <br />RPU engineering staff <br />Civil Construction Performed By: <br />Developer at developer's expense <br />Electrical Work Performed By: <br />RPU field forces <br />Anticipated Start Date: <br />August 1, 2015 <br />Anticipated Duration: <br />One year <br />Coordination Required With: <br />Developer <br />Reimbursements: <br />100% reimbursable by developer <br />FISCAL IMPACT: <br />The capital expenditure for Work Order No. 1515769 is estimated to be $105,000. Sufficient funds are <br />available in Account No. 6130000 - 470601 (Electrical Capital Projects). Consistent with Electric Rules 10 <br />and 11, the expenditure will be fully reimbursed by the developer. <br />