W A T E R E N E R G Y l 1 0 e <br />RIVERSIDE PUBLIC UTILITIES <br />3 -_ W& Board Memorandum <br />PUBLIC UTILITIES <br />BOARD OF PUBLIC UTILITIES DATE: September 5, 2014 <br />ITEM NO: 7 <br />SUBJECT: CONSTRUCTION OF THE ROSE AVENUE AND MOUNTAIN AVENUE 8 -INCH <br />WATER DISTRIBUTION MAIN REPLACEMENT PROJECT — WORK ORDER NO. <br />1319864 <br />ISSUE: <br />The item for Board of Public Utilities consideration is approval of the capital expenditure in the amount of <br />$393,000 to construct the Rose Avenue and Mountain Avenue 8 -Inch Water Distribution Main <br />Replacement Project. <br />RECOMMENDATION: <br />That the Board of Public Utilities approve the capital expenditure of $393,000 for Work Order No. <br />1319864, which includes all design, construction, paving, contract administration, inspection and <br />construction contingency costs for the Rose Avenue and Mountain Avenue 8 -Inch Water Distribution <br />Main Replacement Project. <br />BACKGROUND: <br />The construction of the Rose Avenue and Mountain Avenue 8 -Inch Water Distribution Main Replacement <br />Project is part of Riverside Public Utilities' (RPU) on -going water main replacement program to replace <br />old, undersized and high priority leaky mains. The project area consists of existing 1.5 -inch and 2 -inch <br />steel waterlines that were installed in 1954 and have required numerous repairs due to leaks over the <br />past several years. These pipelines have been prioritized for replacement based on their age, leak <br />history and deficiencies in providing adequate fire protection. These pipelines have reached the upper <br />limit of their useful service life and need to be replaced to increase system reliability and ensure <br />adequate fire flow. <br />The work will generally entail the construction of approximately 1,160 linear feet of 8 -inch ductile iron <br />pipe, 15 water services, three fire hydrants, and four system connections, along with all necessary fittings <br />and appurtenances. The work identified will be constructed by the Water Division's field forces. <br />Once the new water pipelines are installed, RPU will be responsible for standard trench repaving per the <br />Public Works Department standard. Staff will solicit paving bids for paving the trench area from RPU's <br />Paving Contractor Panel. A budgetary estimate for the paving work has been included in this <br />authorization. <br />Other than routine service tie - overs, no service disruptions are anticipated to complete the work of this <br />project. <br />