WATER <br />ERGY <br />PUBLIC UTILITIES <br />BOARD OF PUBLIC UTILITIES <br />RIVERSIDE PUBLIC UTILITIES <br />Board Memorandum <br />DATE: DECEMBER 12, 2014 <br />ITEM NO: 10 <br />SUBJECT: CONSTRUCTION OF THE CENTRAL AND SUNNYSIDE WATER MAIN <br />REPLACEMENT PROJECT — WORK ORDER NO. 1420056 <br />ISSUE: <br />The item for Board of Public Utilities consideration is approval of the capital expenditure in the amount <br />of $1,795,000 to construct the Central and Sunnyside Main Replacement Project. <br />RECOMMENDATION: <br />That the Board of Public Utilities approve the capital expenditure of $1,795,000 for Work Order No. <br />1420056, which includes all design, construction, paving, contract administration, inspection and <br />construction contingency costs for the Central and Sunnyside Water Main Replacement Project. <br />BACKGROUND: <br />The construction of the Central and Sunnyside Water Main Replacement Project is part of Riverside <br />Public Utilities' (RPU) on -going water main replacement program to replace old and high priority leaky <br />mains. The project area consists of existing 2 -inch, 4 -inch, 6 -inch and 12 -inch asbestos cement, cast <br />iron and steel water mains that were installed between 1929 and 1962 and have required numerous <br />repairs due to leaks over the past several years. Based on their leak history, these water pipelines have <br />been identified as high priorities for replacement to increase system reliability. <br />The work will generally entail the construction of approximately 4,600 linear feet of 8 -inch ductile iron <br />pipe, 1,400 linear feet of 12 -inch ductile iron pipe, nineteen fire hydrants, 145 service tie -avers and <br />thirteen system connections, along with all necessary fittings and appurtenances. The work identified <br />will be constructed by the Water Division's field forces. Other than routine service tie - overs, this project <br />is not expected to disrupt service to RPU water customers. <br />Once the new water pipelines are installed, RPU will be responsible for standard trench repaving per <br />the Public Works Department (PW) standard. Staff will solicit paving bids for paving the trench area <br />from RPU's Paving Contractor Panel. A budgetary estimate for the paving work has been included in <br />this authorization. <br />Staff has coordinated with PW regarding the allowable working hours for the project. The work is <br />scheduled to occur during daytime hours, with certain portions of the work to be coordinated to occur <br />during off-peak travel hours. <br />